Madagascar's government requisitioned the Enelec thermal power plant in Toamasina on November 6 under a decree adopted on November 3, L'Express de Madagascar reported. The plant has an announced capacity of 32 megawatts (MW) but supplies at most 14 MW. State utility Jirama produces electricity at about 1,225 ariary (€0.25) a kilowatt-hour and sells it at about 795 ariary (€0.16), the newspaper said.
Analysis: Jirama's tariff covers about 65% of its production cost, by our calculation, leaving a loss of 430 ariary (€0.09) on each kilowatt-hour sold. The state supports the utility with about 300bn ariary (€60mn) a year, according to a parliamentary commission cited in the same report. However, the head of state cited about 1,000bn ariary (€201mn) over one year, a difference that remains unexplained. Independent power producers, fuel suppliers and industrial clients face the most uncertainty over contracts and tariffs. The commission's report on Jirama is expected before the end of 2026.
Source: L'Express de Madagascar, L'Express de Madagascar, 'APPROVISIONNEMENT EN ÉLECTRICITÉ - La Jirama engage plusieurs chantiers pour améliorer le service', Nov 2026, 6 November 2026 and November 2026 and 2026; L'Express de Madagascar, L'Express de Madagascar, 'ÉNERGIE - L'État mise sur l'achat d'urgence de groupes électrogènes', Nov 2026, 2025-2026