Alama ReportMadagascar
Madagascar · From Edition № 001 · Energy, oil & gas

Antananarivo's power shortfall halves to 23.5 MW from a year ago

23.5

The Antananarivo interconnected grid's electricity shortfall fell to an estimated 23.5 megawatts (MW) in September 2026 from 44.9 MW a year earlier, and state utility Jirama forecasts 14.9 MW for November against 27.4 MW in November 2025, according to Jirama figures reported by L'Express de Madagascar. The grid needs 270 MW at the evening peak.

Analysis: The shortfall fell 48% in a year, by our calculation, and the November forecast equals about 6% of evening peak demand. However, the improvement rests partly on emergency diesel generators, which the minister said added 97 MW in six months, while the Andekaleka hydro plant produces 97 MW at peak instead of its usual 116 MW. This leaves supply exposed to fuel deliveries and water levels. Manufacturers, hotels and offices in the capital still need backup power at peak hours. Jirama has published forecasts only to November, and the purchase of 18 MW of further generators has no delivery date.

Source: L'Express de Madagascar, L'Express de Madagascar, 'ÉNERGIE - Le RIA nécessite 270 MW en période de pointe', Oct 2026, September 2026 and September 2025 and June 2026 and July 2026 and November 2026 (forecast) and November 2025 and October 2026; L'Express de Madagascar, L'Express de Madagascar, 'ÉNERGIE - L'État mise sur l'achat d'urgence de groupes électrogènes', Nov 2026, November 2026 and May-October 2026

Every figure comes from the official source named under it. Spotted an error? Write to info@alamareport.com; corrections run in the next issue.

More from this issue

Read the whole issue →More on Energy, oil and gas →

Get the next issue by email

Get the Thursday newsletter

Free every Thursday, in the language of this page: the edition of the country you choose. Every other country is one click away on the site.

Free every Thursday. You can add a second country later, on My account.