Ivory Coast's installed power generation capacity stands at 3,337 megawatts (MW) with the 390 MW Atinkou gas-fired plant, which the prime minister inaugurated on November 6, state news agency AIP said. The plant cost €404mn, or about 265bn FCFA, and has run commercially in combined cycle since December 13, 2025. A day earlier, the government inaugurated the 46 MW Biovea biomass plant at Ayébo, which cost more than 150bn FCFA (€229mn), financial news site Sika Finance said.
Analysis: The two plants illustrate the difference in gas and biomass costs. Biovea cost more than 3.26bn FCFA (€4.97mn) per MW, by our calculation. Its cost per MW is about 4.8 times Atinkou's 0.68bn FCFA (€1.04mn). However, Biovea runs on about 450,000 metric tons a year of local farm residues, while Atinkou depends on gas supply. Atinkou has supplied the grid commercially since December 2025, so its inauguration did not change the 3,337 MW total. The mines and energy ministry's 2027 budget sets a goal of 4,000 MW, AIP said. The goal is 663 MW above current capacity, by our calculation. No date has been announced for reaching it.
Source: Agence Ivoirienne de Presse (state news agency), AIP, 'Le PM Beugré Mambé met en service la centrale thermique d'Atinkou d'une capacité de 390 MW', November 6, 2026, November 2026; Agence Ivoirienne de Presse (state news agency), AIP, November 6, 2026, 2026 and per year; Sika Finance (Abidjan), Sika Finance, 'La Côte d'Ivoire inaugure la plus grande centrale biomasse d'Afrique de l'Ouest', November 6, 2026, 2026; Sika Finance (Abidjan), Sika Finance, November 6, 2026, 2026 and per year; Sika Finance (Abidjan), Sika Finance, November 9, 2026, 2040; Agence Ivoirienne de Presse (state news agency), AIP, 'Chiffré à 738,8 milliards FCFA, le budget 2027 du ministère des Mines adopté par les députés de la CAEF', November 14, 2026, 2027 budget