Eritrea's Dekemhare solar plant supplied 21 megawatts (MW) of the 56 MW of generating capacity available during a supervision visit in late October, the African Development Bank (AfDB) said in a progress report dated November 11. The 30 MW plant, funded with AfDB grants, was completed and commissioned in May 2026. Work on Eritrea's oil-fired power plants has fallen short of a plan to return 96 MW to service by 2025, the report said.
Analysis: Peak demand still exceeds supply. The solar plant provided 37.5% of available capacity during the visit, by our calculation. Unmet peak demand fell to 16 MW from 30 MW when the project began, the report said. This suggests that large power users still face shortfalls at peak hours. Two repaired 22 MW engines and 22 MW of new diesel plant were commissioned in 2024, the report said. These units total 66 MW against 96 MW planned, by our calculation. The AfDB and the government are discussing a restructuring to use uncommitted project funds, including work on up to 10 substations. The AfDB has not announced a date for a decision. The project closes on December 31, 2027.
Source: African Development Bank (AfDB), AfDB, Dekemhare 30 MW Solar PV Grid Connected Project (P-ER-FA0-001), Implementation Progress and Results Report, date of report 11.11.2026 (field mission 26-30 October 2026), published on afdb.org 18 November 2026, Supervision mission, October 26-30, 2026 and Late October / November 2026 (report dated 11.11.2026) and May 2026 and Most recent value, IPR October 2026 and Project baseline (approval 2023) and Target year 2025 and November 2024 (during the AfDB supervision mission) and Earlier in 2024 and Proposed restructuring (no date) and As of report date 11.11.2026 and December 31, 2027